The blame game of KLIA2
The Star Online
> Business
Saturday June 29, 2013
I like to make a few comments on some of the facts and statements that was made by Datuk Azmi Murad, the General Manager of MAHB.
[QUOTE from Para 5-7 ]
The Blame Game of KLIA2
[QUOTE from Para 5-7 ]
According to MAHB operations senior general manager Datuk
Azmi Murad, the last-minute instructions are
just minor changes needed by stakeholders, and this doesn't affect the
completion date of the seven sectors of the terminal itself.
Among the requests are the addition
of 45 more immigration counters, and additional ticket booths and counters.
“The instructions for the
immigration counters are a valid point, and the contractors can apply for
extension of time (EOT) to justify the extension. This may take only a further
two to four weeks to complete, but does not justify an EOT for one year. The JV
(referring to UEMC-Bina Puri JV, who is the Main Contractor for the Main terminal Building and Satellite Building & Associated works) already has enough time to complete the works before June,” he says.
[UNQUOTE]
My remarks:
As
reported, Datuk Azmi acknowledged that “the instructions for the immigration
counters are a valid point and the Contractors can apply for EOT to justify the
extension.” (ibid)
But what was puzzling is: Datuk Azmi had acknowledged the
VO works for the extra 45 immigration counters and that such additional works (or what we call, 'Variation Order' works) may take 2 to 4 weeks to
complete. This statement in itself means that the Contractors are contractually
entitled to EOT. The fact is, this VO Instruction was issued on 29th May 2013 and the Contract Completion Date is 15th June 2013. So, would MAHB still expects the Contractor to complete the works by 15th June 2013? And if Datuk Azmi admitted that it may only take 2 to 4 weeks to complete, then the Contract Administrator (CA) must perform his fiduciary duty by granting the Extension of Time (EOT) accordingly. However, the CA failed to do so, and instead chose to issue the Certificate for Non Completion on 16th June 2013 and thereof imposed the LAD. From the presentations made at the press conference on 28th June 2013 at the KLIA2 site, there were quite many instructions issued by MAHB for additional works and modification of designs during the period between March to June 2013. The period between March to June was significant as the earlier EOT granted was made on 15th March 2013. As such, it was imperative that the CA would have to assess the EOT fairly and reasonably.
It is trite construction law that there will be implied into every construction contract terms whereby the owner shall cause the Contract Administrator (CA) to act fairly, impartially and within the times required by the contract conditions. It is also understood that the CA has a legal obligation to so act, using his 'professional skills' and 'best endevours' to reach the correct decision rather than necessarily deciding in the owner's favour.
It is trite construction law that there will be implied into every construction contract terms whereby the owner shall cause the Contract Administrator (CA) to act fairly, impartially and within the times required by the contract conditions. It is also understood that the CA has a legal obligation to so act, using his 'professional skills' and 'best endevours' to reach the correct decision rather than necessarily deciding in the owner's favour.
On the
legal perspective, the Employer and/or his Contract Administrator (CA) had
wrongfully issued the Certificate for Non Completion (CNC) because it is trite law that the CA is duty bound, before issuing the CNC, to act
fairly and reasonably, by assessing and exhausting all the events of delay caused by
the Employer before he forms his opinion, and that the Contractor has no more valid
entitlement to any EOT. However, the Variation Order instruction to add 45
extra immigration counters was issued only on May 29, 2013 while the CNC was
issued on 16th June 2013, i.e. 2 weeks later.
Clearly, the Contract Administrators are ignorant of the law of contracts. What is puzzling is the fact that MAHB has a legal department filled with legal experts.
In Peak
Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) the Court of Appeal held that Peak Construction
was not entitled to recover Liquidated Damages from McKinney. The Court of
Appeal found that at least part of the 58-week delay had been caused by the
corporation itself, and no attempt had been made by the corporation to extend
time. Accordingly, there was no date from which Liquidated Damages under the
main contract could begin. Lord Salmon held “If the failure to complete on time
is due to the fault of both the employer and the contractor, in my view, the clause
does not bite. I cannot see how, in the ordinary course, the employer can
insist on compliance with a condition if it is partly his own fault that it
cannot be fulfilled.”
The Court had held that:
'Notwithstanding that the Contractor is not entitled to or has not
claimed an extension of time, the Superintendent Officer (SO) or CA may at any
time and from time to time before the issue of the Certificate for Non
Completion (CNC) by notice in writing to the Contractor extend the time for
practical completion for any reason.'
In such a case where MAHB and his CA has issued the CNC and LAD notice, Edmund Davies has this advice:
“The
stipulated time for completion having ceased to be applicable by reason of the
employer’s own default and the extension clause having no application to that,
it seems to follow that there is in such a case no date from which liquidated
damages could run and the right to recover them has gone.”
Importantly, common law courts have construed extension of time clauses
narrowly when determining their application to events of owner-caused delay. By
way of example, courts have held that clauses providing general grounds for
delay, including the catch all 'other causes beyond the contractor's
control' and 'for any cause not under the control of the builders',
will not cover specific acts of prevention by an owner. As stated by Professor
Wallace QC as editor of the 11th edition of Hudson's Building and
Engineering Contracts, it is likely courts interpreted these clauses
narrowly because of their dislike of, and willingness to invalidate, liquidated
damages provisions for any event not expressly provided for in a contract or
within the contractor's scope of responsibility.
A well-known example of the prevention principle is
the 1971 English Court of Appeal judgment, Peak Construction (Liverpool)
Limited v McKinney Foundations Limited.
In Summary,
it can be observed that MAHB had shot their own feet by issuing the CNC and
invoking the LAD while at the same time, they acknowledged that they had
knowledge of the delay events caused by the issuance of Written Instruction for Variation (legally
classified as Employer’s Delay) whereof MAHB and his CA had failed to grant the necessary EOT to
the Contractor. In this circumstances, the Contract will become time at large and any wrongful
deductions enforced unto the contractors’ payment will be construed as an Act
of Prevention to Completion and a Fundamental Breach of Contract that activates
Section 56 and Section 74 of the Contracts Act 1950.
PARA 11 of the News report
[QUOTE]
Besides the incomplete terminal, the taxiway and the new
Runway 3 are also unfinished, which according to MAHB would not prevent KLIA2
from a delayed opening as it can direct air traffic to KLIA2 via the existing
Runway 2, assuming if the terminal was operational.
[UNQUOTE]
REVIEW & LEGAL OPINION
ON PARA 11
According
to the report, MAHB states that “the taxiway and new Runway 3 (contracted to other corporations) which are
unfinished till today (where EOT was granted until August 2013) would not prevent KLIA2 from a delayed opening (in reference to June 15, 2013 completion date for Main Terminal Building & Satellite Building Contract) as it can direct air
traffic to KLIA2 via the existing Runway2, assuming if the terminal was
operational.”
I am puzzled and flabergasted! How is it possible for MAHB to assume that the terminal can be
operational without the planned taxiway at the Main Terminal Building and Satellite Building?
The taxiway and runway has not been completed and will not complete till probably September 2013. So how do the airplanes get to the link-bridge to
allow the passengers disembark? And would DCA permit the airplane to land at
the airport where construction works and heavy machinery and
equipment are still plying and working at the airport sites? What are the safety
compliance standards and requirements specified by ICAO, IATA and NACO for this
LCCT? The photographic proof and evidence of the existing site conditions will convince any judges to
dump this argument. MAHB prides itself of their international standards of
Management of Airports and such statement will be embarrassing to potential
airport owners.
PARA 12 [QUOTE]
First envisioned to become a low cost carrier terminal
(LCCT) with a price tag of RM1.9bil, it has ballooned to RM4bil featuring
state-of-the-art specifications. It is a LCCT but definitely not a low cost
terminal.
[UNQUOTE]
REVIEW & OPINION ON
PARA 12
Rightly
said, this KLIA2 is not a “Low Cost Terminal” as envisaged in the tender
document. The design was intended and tendered out to the Contractors as LCCT
but the enforcement of the Concept Design Consultants (CDC) who forced unto the
Contractors to deliver a detailed design that encompasses high state of the art
specifications that ultimately produced a High Cost Terminal (similar or of
much higher standards and specification compared to the current KLIA Terminal)
for a Low Cost Carrier Terminal Design-and-Build Contract which may be
arbitrated in a legal forum at a later date.